The wind farm was granted planning consent in 2012 and comprises six turbines, measuring 126.5m high to the tip of the blade.
Construction work began in March 2014 with turbine deliveries taking place in the autumn. All six Nordex turbines were erected by the beginning of December 2014..
Jack's Lane Wind Farm became fully operational in April 2015, triggering community benefits of £75,000 a year.